|
Andrew Logsdon's experience
at Toyota's Paint Project Group
Andrew
Logsdon, a mechanical engineering major who graduated from Lexington
Catholic H.S., spent fall 2006 on his second work session for
Toyota
Engineering and Manufacturing
North America (TEMA) with
TEMA
Body Production Engineering (BPE) – Paint Project Group
Erlanger
, KY
Physical
Work Location: TMMK Georgetown , KY
Experience
in project management
I enjoyed this term a lot more than my first because I got
the hands on, plant experience I was hoping for. All of my projects
were supportive of a $16 Million Top Coat Booth Refurbishment project
that was led by my TEMA BPE Paint Projects Group.
We
completed construction and installation of the new robots in Top Coat
B (TCB) Booth, and completed the oven extension for TCB that was required
by the faster takt time the robots could achieve.
My
first assignment was TCB Punchlist management and major item investigations.
I created Investigation Reports on serious issues encountered in this
project and followed up on each root cause and countermeasure. Next,
I helped our SEIBI (Robot Teaching) team with Quality trials to achieve
standard specifications.
My
largest project was TCB Stage 1 Auto Equipment Demolition. I led this
project which involved the removal of 15 year old equipment that the
new robots were replacing. I complted all the planning and coordination
that we would normally pay a General Contractor (GC) to do, and in the
process saved $180,000 that our normal GC quoted for the job. This was
a perfect example of TEMA's Self Reliance initiative as they aspire
to be fully independent in North America from the Japanese assistance
of Toyota .
TEMA's
main work is change preparation and execution, whether it is for a major
model change or replacement of depreciated equipment; everything comes
down to project management. Much of the work is given to a general contractor
and as a TEMA employee, you plan, coordinate, and manage the projects
from a broad point of view.
This
term really developed my skills in the areas of communication and planning.
I met with all the sub-contractors to show them the tasks and in turn,
I learned from their expertise about the exact way the work would be
executed. I would then plan using standard Toyota documents which would
coordinate all required groups (TMMK project team, security, facilities,
sub-contractors, etc.) via meetings and walk-thru's for the demolition
activities.
In addition
to project management, there were numerous examples where experiences
related to my past academic studies. A good example was the Oven Extension
part of this TC Refurbishment project. The increased capability of the
new robots allowed us to shutdown TC C Booth after the new robots were
put in TCA and TCB. To meet demand with one less booth meant increasing
the conveyor speed. In order to maintain the keep time within the cure
window, now that the conveyor was moving faster, the length of the oven
needed to be increased. This was understandable from classes on Heat
Transfer. During the quality trials for TCB robots for achieving standard
film thickness, I used a digital paint thickness gauge that measured
the thickness of the paint by passing an eddy current through the paint
and into the metal. The strength of the eddy current determined the
paint's thickness within +/-1 micron. It was cool to see the theory
from Physics classes applied in the real world.
I
continued learning the requirements needed to achieve a quality paint
job. This might include the film build, color hiding properties of the
Primer and Base Coats, and the effect the robot's high voltage electric
fields have on the metal flake behavior in mica colors.
This
TC Refurbishment project is interesting because it is being done while
normal production is occurring. This means that our work took place
mainly on weekends and between shifts. With this in mind, a typical
day for me would start around 6:30AM. Normally there is generous flexibility
from TEMA on start times but for this project, we had contractors doing
electrical and piping work outside of the paint booths, therefore allowing
it to happen during the week. I would get set up for the day then meet
the contractors at 7 and 7:30AM. Mainly I would check that they had
reviewed their Job Hazard Analysis forms, signed them off, and they
would tell me their activities so I could make sure it would have no
impact on production. After this I would come back to my desk, check
my email, and prepare for coordination meetings that took place on Tuesdays
and Wednesdays in preparation for the weekend work. After these meetings
at 9 and 10AM, I would spend the majority of the day ironing out plans
for upcoming activities. This may include coordinating with contractors
or having them bid smaller jobs that would arise. For this project,
there always seemed to be something new each day that I needed to support
because it was imperative that all the construction and installation
activities didn't have any impact on production.
Of
the income I received from this co-op rotation, approximately 1/3 of
it went to my actual living expenses. This included a townhouse. Separate
from my rent were utilities including electric, water, and gas. I also
was enjoying DVR digital-recordable cable with high speed internet,
cell phone, and liability insurance on three separate vehicles. My girlfriend
and I ate out quite often and for the first time I had no stress from
maintaining a positive amount in my checking account. I was able to
save enough to pay tuition for two semesters of classes. The savings
were a lot more than I anticipated.
|